Building Construction Timeline

BUILDING UPDATES

Construction Update: June 12, 2019 Lower Level: Framing & plumbing being installed. Level One. Framing, Plumbing, & Electrical being installed. Installation of elevated slabs in kitchen and bathrooms complete. Mockups on the column finish and access floor ready for review. Level Two: Formwork was being stripped. Level Three: Columns and shear walls complete. Formwork for[…]